Build a handover register
Create one row for each repository, build pipeline, runtime, database, model account and scheduled job. Record the business owner, technical owner, billing account, recovery contact and location of the access procedure. Store credential references in the register. Keep the actual secrets in your secret manager.
Rehearse the first independent release
Ask a company engineer to change one staging setting, deploy the reviewed revision and locate its release identifier. The vendor observes and notes where the runbook fails. Repeat the exercise with a different operator after fixing the instructions. A successful vendor-led screen share does not show whether either operator can do the work alone.
Recover data as well as software
Use an isolated database for the rehearsal. Restore a recent backup and verify a known business record plus its attachments. Then ask the operator to trace a single failed request from its public identifier into the relevant logs. Keep the measured time and the missing permissions with the acceptance record.
| Handover item | Proof to retain |
|---|---|
| Source and release | Commit, build record, deploying identity and working rollback procedure. |
| Production dependencies | Inventory of external APIs, quotas, billing owners and renewal dates. |
| Data recovery | Restore timestamp, record checked and person who performed it. |
| Vendor exit | Revoked test identity and a successful subsequent run under a company account. |
A handover rehearsal with the vendor watching
A supplier says the deployment is documented. The buyer’s on-call engineer opens a clean session and tries to release a small test change. The build succeeds, but the final approval still goes to a vendor-owned account. A repository transfer alone would have left that dependency undiscovered.
Put the vendor in an observer role. Have the buyer deploy, read the release logs, reverse the change and restore a sample record. Note every instruction that had to arrive by chat and move it into the runbook.
What to keep
Buyer-owned release and rollback logs, a restored test record, and a named operator who repeated the exercise with the corrected instructions.
When to pause
Leave the handover milestone open until the buyer controls the approval path and can complete the rehearsal again without a supplier credential.
Make the decision
Tie final acceptance to the exercises that matter for this application. A successful deployment cannot compensate for an untested restore. Assign any outstanding recovery or monitoring task to a named person with a deadline and agree who supports incidents in the meantime.
Open the buyer worksheet →